This open house ran May 31-June 23, 2024. The content may no longer be current.

Please visit the project webpage for up-to-date information.

All dates are estimates and subject to change.

 

 

 
  • Design

    2019-2023
  • Right-of-way acquisition

    2021-2023
  • Erosion control

    June 2024
  • Stage one construction

    June-July 2024
  • Stage two construction

    July-October 2024

    Includes closure of River Road south of the intersection for about 110 days.

  • Stage three construction

    October 2024
  • Stage four construction

    November 2024-April 2025

    Includes closure of River Road north of the intersection for about 70 days.